- Manufacturers must comply with NAECA, so HVAC equipment purchased by builders should automatically comply with code requirements.
- Thermostats are required for each separate HVAC system.
- The 2003 IECC has minimum insulation thicknesses for HVAC piping by type of piping system, pipe size, and fluid temperature range.
- Duct insulation requirements in the IECC depend on the location of the building (HDD), the type of duct, and the location of the duct.
- All duct joints, seams, and connections must be securely fastened with welds, gaskets, mastics (adhesives), mastic-plus-embedded-fabric, or tapes. "Duct tape" is not permitted.